If a PO line is tied to a Project, you can’t adjust the cost on either the Project Material Plan or the PO, but there is a way to update them without a Change Order. This does not apply to Dropship POs.
Table of Contents | ||||
---|---|---|---|---|
|
Solution
You will need to remove the Project tie and update the cost on the Project Material Plan. Then you will update the PO Tie / Cost and re-attach to the Project in PO Query/Change
Table of Contents | ||||
---|---|---|---|---|
|
Project Material Plan Updates
...