The Assembly Line Inquiry screen allows easy viewing of line capacity in a convenient calendar format. Each day of the month indicates the number of scheduled work units and remaining work unit capacity. Numbers in yellow represent scheduled work units on that day. White numbers represent available work unit capacity for the day. To view the schedule for a different assembly line, simply click on the assembly line code and the calendar will change to reflect that assembly line. Use the << and < buttons to view previous year and previous month, respectively. The > and >> buttons allow you to view next month and next year, respectively.
PRD > Assembly Line Inquiry

Any time you see a number in red it means the line is scheduled over capacity. You can view the scheduled work orders for a particular day by double-clicking and the box containing the day of the month. To view the work orders for the 9th, double-click on the gray box for the 9th. The screen will flip over to the Schedule Detail tab and display the work orders schedule for the 9th.

To view the details of the work order, double-click on the work order number of the left. This will open the Work Order Inquiry screen and display details of the work order. To go back to the schedule, click on the Schedule tab. To view work orders currently in production on an assembly line, click on the In Process tab.

To view the details of the work order, double-click on the work order number of the left. This will open the Work Order Inquiry screen and display details of the work order. 