Alpha Change Orders
Overview
Alpha Change Orders will make adjustments to the material plan of a project without officially being processed. This allows you to adjust or delete the Change Order before it is official. Once it is ready, you can process it to become a Change Order.
Step-by-Step Guides
Creating an Alpha Change Order
To Create an Alpha Change Order, select the “Alpha” radio button when entering a Project Change Order.
Go to the Change Order Entry Screen
Click “Change Order” Button on the Project Material Plan
P/A>Change Orders>Change Order Entry
Select “Alpha” Radio Button
Enter your Change Order Details
Process the Change Order
Open/Edit/Delete/Process Alpha Change Orders
Once you process the Alpha Change Order, it enters the Alpha Change Order holding tank. To access it, you will need to double-click on the Alpha Change Order total on the Money tab of your project.
Open Alpha Change Order Holding Tank
Open Project
P/A>Projects>Project Entry/Edit
Go under the “Money” tab
Double-Click on Alpha Change Order Total
Edit Alpha Change Orders
Once you open the Alpha Change Order holding tank, you can select your Change Order and Edit using the fields. Hit Process to update the Change Order.
Open Alpha Change Order Holding Tank
Click on the Change Order you want to adjust
Enter the changes in the fields at the bottom
Hit Process to update the Change Order
Delete Alpha Change Order
After opening the Alpha Change Order holding tank, select your Change Order, and Hit the Delete button.
Open Alpha Change Order Holding Tank
Click on Change Order to Delete
Hit Delete Button on the bottom-right side of the screen
Say “Yes” to prompt
Process Alpha Change Orders
To make an Alpha Change Order Official, you will need to Process it with another Change Order.
Go to the Change Order Entry Screen
Click “Change Order” Button on the Project Material Plan
P/A>Change Orders>Change Order Entry
Select “Change Order” Radio button (default)
Select the “Alpha” Line Type
Select your Alpha Change Orders in the popup
Double-click
Check the box
Hit “Process” to pull the Alpha Change Order into your Change Order
Double check everything is correct on the Change Order
Process the Change Order
Click on the Lightning Bolt